Evaluation and Qualification Criteria Calculator

Calculate the project-specific values to insert in Section III before issuing the bidding document.

PPMO SBD · September 2026Works above NPR 20 millionPass / fail qualification
01

Contract basis

Use the estimate without VAT and contingencies, but including provisional sums.

02

Qualification choices

Defaults follow the ordinary ranges stated in the SBD. Record reasons for project-specific reductions.

03

Key activities

Only contractor-executed activities representing at least 10% of the estimate should be considered.

No key activity added. Add only measurable activities that meet the SBD selection conditions.

04

Subcontract packages

Add this only when Section 2.5 permits specified work to be subcontracted.

Subcontracting qualification criteria will stay out of the draft unless a package is added.

05

Evaluation choices

Project-specific evaluation factors must be stated in advance or marked not permitted.

SBD scope matched

Insert-ready Section III schedule

Untitled works procurement

Single contract
Eligibility controlsSection III 2.1
2.1.1–2.1.5
Core eligibility

Nationality, no conflict of interest, Government or Development Partner eligibility, government-owned entity conditions and UN eligibility under ITB 4.2 to 4.7.

Letter of Technical Bid · Forms ELI-1 and ELI-2 with attachments where required
2.1.6
Running contracts

The Bidder must not yet have secured five construction contracts through open competitive bidding under ITB 4.9.

Form ELI-3 · apply the SBD exclusions for pre-2078-12-03 contracts, accepted works under Rule 117 and foreign-assisted contracts
2.1.7
Domestic registration and tax documents

Firm registration, business licence, VAT/PAN and tax clearance, return evidence or time-extension evidence for the fiscal year to be inserted.

Document attachments
Calculated minimumsFor the subject contract
2.3.2 TurnoverNPR 5,00,00,0001.5 × V/T
2.3.3 Financial resourcesNPR 83,34,000Straight-line cash flow
2.3.4 Bid capacityNPR 5,00,00,000100% of V
2.4.2(a) Similar contractNPR 2,00,00,00040% of V
Contract calculation sheetSection III 2.3 and 2.4

Contract 1

NPR 5,00,00,000 · 18 months · Non-complex works
Average annual construction turnover
NPR 5,00,00,000
Financial resources for 3 months
NPR 83,34,000
Required bid capacity
NPR 5,00,00,000
One similar contract within last 10 years
NPR 2,00,00,000 40% of V

Financial evidence: turnover uses Form FIN-2 and the best three years within the last ten fiscal years, net of VAT and indexed to present value. Financial resources use Form FIN-3. Bidder capacity is tested through FIN-4 and FIN-5 as (5 × A) − B.

Similar-work evidence: use Form EXP-2(a). Contract values are net of VAT and adjusted to present value using the Nepal Rastra Bank wholesale price index.

Fixed and selected criteriaComplete before issue
ReferenceRequirement to insert
2.2.1

Pending litigation must not exceed 50% of the Bidder's net worth.Form LIT-1

2.3.1

Audited financial statements for the last 3 years; latest-year net worth must be positive.Form FIN-1 with attachments

2.4.1

General construction experience for at least the last 5 years.Form EXP-1

2.4.2(a)

Similarity based on physical size, complexity, methods, technology or other stated characteristics.Form EXP-2(a)

2.1.7

Firm registration, business licence, VAT/PAN and tax clearance or return evidence for the fiscal year to be inserted.

Joint venture financial matrixAll partners combined must meet 100%
CriterionCombinedEach partner · 25%One partner · 40%
TurnoverNPR 5,00,00,000NPR 1,25,00,000NPR 2,00,00,000
Financial resourcesNPR 83,34,000NPR 20,84,000NPR 33,34,000
Bid capacityNPR 5,00,00,000NPR 1,25,00,000NPR 2,00,00,000
Key activitiesSection III 2.4.2(b)

No key activity has been selected.

Check market availability, avoid duplication with the similar-contract definition, account for adverse climate, and record the basis for every selected key activity.

Evaluation clausesSection III 1.1 to 1.6
  1. Permitted criteria only

    Use only ITB 35.2(a) to (e) and the criteria disclosed in Section III. Do not introduce an unstated factor during evaluation.

  2. Technical proposal

    Assess work methods, scheduling, material sourcing and capacity to mobilize key personnel and equipment. Personnel or equipment noncompliance stated in Section VI is clarified and rectified before award, rather than used by itself as a rejection ground.

  3. Multiple contracts

    Not applicable unless the procurement is packaged into multiple contracts.

  4. Financial comparison

    Subject to qualification, apply the substantially responsive bid closest to the Average Bid Price rule stated in Section III 1.3.

  5. Completion time

    Alternative completion time is not permitted.

  6. Technical alternatives

    Alternative technical solutions are not permitted.

  7. Nonmaterial nonconformities

    Use the standard Section III 1.6 wording pursuant to ITB 31.3. Evaluate quantifiable nonmaterial nonconformities but exclude omission of BoQ prices.

Review before issueProfessional checks
  • Verify the approved estimate components and rounding against the signed cost estimate.
  • Complete personnel and equipment requirements in Section VI without restrictive or irrelevant conditions.
  • Delete all guidance notes, brackets and unused alternatives from the final bidding document.
  • Obtain competent-authority approval and confirm any later PPA, PPR or PPMO instruction before publication.

What the calculator does not decide

It does not decide whether a work is complex, define similar experience, select key activities, set personnel or equipment, or replace approval by the competent authority. Those choices must follow the actual scope, design, estimate, market conditions and current procurement law.